CURRENT INFORMATION

Operational information

Daily storage inventory in Zone MND ESG
From:
To:
Date: Current capacity in TWh Withdrawals (GWh/day) Injections (GWh/day)
28.3.2024 1.755 1.400 0
27.3.2024 1.756 0 0
26.3.2024 1.756 0 2.136
25.3.2024 1.754 0 0
24.3.2024 1.754 0 0
23.3.2024 1.754 0 0
22.3.2024 1.754 0 1.848
Shutdowns and maintenance
Date of Limitation Description of Storage Services Limitation – Zone Other Restrictions Additional Information
6.2. – 20.2.2023 100% of withdrawal rates valid at time of limitation, injection rates unaffected   Reactive maintenance at UGS Hähnlein due to technical failure
23.6.2021, 4 hrs 50% of injection rates valid at time of limitation   Maintenance – UGS Haehnlein
1.10.-20.10.2018 10% of withdrawal rate will not/is not available at time of limitation   Workover Stockstadt S1 – UGS Stockstadt
1.9.-20.9.2018 15% of withdrawal rate will not/is not available at time of limitationung nicht verfügbar   Installation of filterseparator UGS Hähnlein
20.11.-24.11.2017 50% of withdrawal and injection rates valid at time of limitation   Installation of turbine (commercial measurement ) UGS Stockstadt
31.8.2016 (7:00-17:00) 50% of withdrawal rates valid at time of limitation   Maintenance at UGS Hähnlein
30.8.2016 (7:00-17:00) 50% of injection rates valid at time of limitation   Maintenance at UGS Hähnlein
4.8.2016 (7:00-17:00) 50% of withdrawal/injection rates valid at time of limitation   Maintenance at UGS Hähnlein
19.7.2016-21.7.2016 50% of withdrawal/injection rates valid at time of limitation  

Maintenance on Main-Neckar pipeline (see OGE web pages)