CURRENT INFORMATION

Operational information

Daily storage inventory in Zone MND ESG
From:
To:
Date: Current capacity in TWh Withdrawals (GWh/day) Injections (GWh/day)
14.6.2025 1.217 0 22.482
13.6.2025 1.195 0 14.696
12.6.2025 1.180 0 16.422
11.6.2025 1.164 0 12.627
10.6.2025 1.151 0 12.032
9.6.2025 1.139 0 24.552
8.6.2025 1.115 0 25.035
Shutdowns and maintenance
Date of Limitation Description of Storage Services Limitation – Zone Other Restrictions Additional Information
16.9. - 18.9.2024, 6:00 100% of withdrawal rates valid at time of limitation, injection rates unaffected   Reactive maintenance due to technical failure
14.8. - 13.9.2024 63% of withdrawal rate will not/is not available at time of limitation   TSO Maintenance - Main-Neckar pipeline
6.2. – 20.2.2023 100% of withdrawal rates valid at time of limitation, injection rates unaffected   Reactive maintenance at UGS Hähnlein due to technical failure
23.6.2021, 4 hrs 50% of injection rates valid at time of limitation   Maintenance – UGS Haehnlein
1.10.-20.10.2018 10% of withdrawal rate will not/is not available at time of limitation   Workover Stockstadt S1 – UGS Stockstadt
1.9.-20.9.2018 15% of withdrawal rate will not/is not available at time of limitationung nicht verfügbar   Installation of filterseparator UGS Hähnlein
20.11.-24.11.2017 50% of withdrawal and injection rates valid at time of limitation   Installation of turbine (commercial measurement ) UGS Stockstadt
31.8.2016 (7:00-17:00) 50% of withdrawal rates valid at time of limitation   Maintenance at UGS Hähnlein
30.8.2016 (7:00-17:00) 50% of injection rates valid at time of limitation   Maintenance at UGS Hähnlein
4.8.2016 (7:00-17:00) 50% of withdrawal/injection rates valid at time of limitation   Maintenance at UGS Hähnlein
19.7.2016-21.7.2016 50% of withdrawal/injection rates valid at time of limitation  

Maintenance on Main-Neckar pipeline (see OGE web pages)